Keep your interconnection application moving.
ONC-FS-104 Rev 04
Large Load Facilities StudyOncorIssued yesterday
Illustrative study figure. Engineering review required.
Scroll to inspect the drawing.
What changed
New revision- 34.5 kV fault duty
- 27.6 kA → 33.8 kA
- Switchgear minimum
- 40 kA
- SG-01 rated
- 31.5 kA
Open an engineering review of SG-01
Paused- Action
- Create engineering review for SG-01
- Fault duty
- 27.6 kA to 33.8 kA
- Rating
- 31.5 kA on PO-24031, 40 kA required
- Reviewer
- Jordan Lee
Follow a utility requirement.
See which equipment and project records a revised utility study affects.
- 1The substation the project has to energize.
- 2Each piece of equipment is a symbol on the single-line.
- 3One record per piece, under one tag.
- 4The utility raises fault duty to 33.8 kA.
- 5Only SG-01 and four records react.
- 6Four revisions, ready for review.

Northstar 300 MW AI Campus · 138 / 34.5 kV substation
- ONC-FS-104 · Rev 04 · §4.3SG-01 is 31.5 kA in the design and on the orderFault duty 27.6 kA to 33.8 kA. Switchgear minimum 40 kA.
- Switchgear submittalNAC-EQ-221 · Rev 0231.5 kA to 40 kAPrepared for review
- Purchase orderPO-24031Change request, 40 kA lineupPrepared for review
- Protection studyNAC-E-214 · Rev 03Rerun at 33.8 kAPrepared for review
- Schedule activityNAC-CX-4410Retest before NAC-MIL-5000Prepared for review
Illustrative substation and single-line.
Catch the mismatch before it reaches site.
The utility has revised its requirement. The equipment order still carries the old rating. Vela connects the two.
SG-01 · Equipment duty
The order is below the new requirement.
- SG-01 on orderPO-24031
- 31.5 kA
- Revised fault dutyRev 04 · §4.3
- 33.8 kA
- Required equipment ratingRev 04 minimum
- 40 kA
Trace the requirement
- Utility studyONC-FS-104 Rev 04
Fault duty changed from 27.6 kA to 33.8 kA.
- Equipment registerNAC-PROC-012
SG-01 still carries 31.5 kA.
- Purchase orderPO-24031
Reconcile the rating before release of a change.